How to change the two component gasket machine bucket

Two-component glue machine bucket, as the name suggests, is used to transport or pump glue fluid equipment, two-component glue machine equipment is mainly used to transport high viscosity fluid medium, today let's take a look at the replacement of a few steps of the two-component glue machine bucket, but before learning we first need to understand some knowledge of the CNC PU foam seal gasket machine.

SZD-4-2-ZB CNC PU foam sealing strip gasket machine

What are the characteristics of the CNC PU foam seal gasket machine?

1, with high pressure air in the set time, the use of foot switch or automatic liquid out.

2. The controller of the dispensing machine has the function of dropping, connecting and timing glue dropping; Drip is directly triggered by the foot switch drops glue, and can be controlled by time dispensing accuracy; Connecting is to use the closing time of the foot pedal to control the dripping time; Timing glue drop is to trigger the switch through the time control glue drop.

3. Automatic gluing machine adopts high precision digital timing controller to accurately control each titration time, accurate to millisecond, correctly control liquid material flow, never waste liquid material.

4. As long as the air pressure is adjusted, the glue time and the appropriate needle nozzle are selected, the amount and time of each injection can be easily changed.

5, adjust the automatic dispensing valve tail adjusting screw and glue pressure can control the size of the glue produced. Glue adjustment screw clockwise downward to reduce the amount of glue, reverse clock direction to increase the amount of glue.

How to replace the two component glue machine bucket?

1. Turn off the intake pressure of the air pump.

2. Open the rubber valve to release the pressure of the internal system.

3. Open the pressure disc blowpipe valve.

4. Switch the lifting control valve to the "UP" position.

5. The pressure disc will be lifted from the rubber bucket, and finally out of the rubber bucket to the appropriate position to replace the rubber bucket.

6. Remove the empty rubber bucket from the device frame.

7. Close the pressure disc blowpipe valve.

8. Clean the two sealing rings of the pressure disc and make the surface clean.

9. Carefully check whether the new rubber bucket has dents or other damage. Do not use damaged rubber bucket, this will damage the pressure plate.

10. Put the new rubber bucket on the center position of the equipment base, located below the pressure plate.

11. Grease the sealing ring of the pressure disc.

12. Remove the exhaust and rubber outlet lever.

13. Dial the lifting control valve to the "Down" position and slowly move the pressure disc into the open rubber bucket. To stop pressure plate movement, the lift control valve can be shifted to the Neutral position.

14 pressure disc continue to press down, when there is a stable rubber outflow at the exhaust and rubber outlet, install the exhaust and rubber outlet stop rod back to the pressure disc and tighten on the joint.

15.After the bucket changing step is completed, open the intake switch of the air pump and work normally.

What if the seal always falls off?

1, prevent rain (water), dust, pollution gas intrusion;

2, prevent vibration, noise, heat into the room;

3.Prevent corrosive media from eroding product components.

These are about how to replace the two component glue machine bucket steps and other relevant knowledge about the CNC PU foam seal gasket machine. Read the instructions carefully and consult an experienced technician before proceeding. At the same time, I also want to seriously recommend SHZ Power, a professional manufacturer in the field of CNC PU foam seal gasket machine in China. If you are interested, you can click on the homepage of the website to further find out about the knowledge of CNC PU foam seal gasket machine, looking forward to your arrival.                                                 